The City of Enid has released a list of construction projects occurring this week.
- West Broadway Ave.
- Parking enclosure
- December 2024 – July 2025
- Parking enclosure
- North Cleveland St.
- Asphalt work
- Jan. 13 – April 18
- Asphalt work
- East Willow Rd.
- Waterline installation
- Feb. 3 – Oct. 10
- Waterline installation
- 42nd St.
- Street repairs
- April 14 – 25
- Street repairs
- Leona Mitchell Blvd.
- Concrete repairs
- April 1 – 11
- Concrete repairs
- North Garland Rd.
- Full concrete repairs
- March 31 – April 14
- Full concrete repairs
- Ponca Ave.
- Full concrete repairs
- March 31 – April 14
- Full concrete repairs
- North 27th St.
- Asphalt Overlay
- April 10 – 11
- Asphalt Overlay
- East Cherokee Ave.
- Utility work
- April 1 – Oct. 27
- Utility work
- East Cottonwood Ave.
- Utility work
- April 1 – July 30
- Utility work
For more information regarding road projects, visit the Enid webpage here.