The City of Enid has announced the construction projects scheduled for this week.
These projects involve road closures that are either currently underway or planned to start in the coming days. The list of projects includes several key areas where construction work will take place, affecting local traffic and commuting patterns:
- West Broadway Ave.
- Parking closure | Dec. 2024 – July 2025
- North Cleveland St.
- Asphalt work | Jan. 13 – April 18
- East Willow Rd.
- Waterline installation | Feb. 3 – Oct. 10
- 42nd St.
- Street repairs | April 14 – 25
- North Garland Rd.
- Full concrete repairs | March 31 – April 14
- Ponca Ave.
- Full concrete repairs | March 31 – April 14
- East Cherokee Ave.
- Utility work | April 1 – Oct. 27
- East Cottonwood Ave.
- Utility work | April 1 – July 30
- Lakeview Dr.
- Planned water outage | April 15 from 8 a.m. to 3 p.m.
- Cleveland Dr.
- Lane closure | April 10 – 15
- East Chestnut Ave.
- Waterline construction | April 14-28
- East Cherry and East 19th St.
- Concrete repairs | April 12 to May 3